Horizon Middle School Renovation & Expansion
Timeline:
Design Development | September 25 – December 10, 2018 |
Construction Documents Development | December 10, 2018 – April 1, 2019 |
Groundbreaking Ceremony | March 27, 2019, 5:30pm |
Students/Staff Last Day at Horizon | March 29, 2019 |
Spring Break | April 1-5, 2019 |
Site Preparation Begins | April 1, 2019 |
Students Start School at Horizon North
10304 E 9th Avenue (Former U-High, adjacent to Valley Christian School) See Bus Routes Below
|
April 8, 2019 |
Construction Period | June 3, 2019 – August 5, 2020 |
Horizon Construction Behind the Fence Tour | January 16, 2020 |
Horizon Dedication | TBD |
Students Start in the Renovated Horizon | September 2020 |
Thank you for celebrating the Horizon Middle School Groundbreaking with us in March 2019 the Behind the Fence Tour on January 16, 2020 and again for the building dedication in fall of 2020.
Click here for more information about the school
HORIZON RENOVATION QUICK FACTS:
Principal: Josh Wolcott
Address: 3915 S Pines Road, Spokane Valley, WA 99206
Architect | Contractor | Process: NAC Architecture | LK Clark Construction | General Contractor/Construction Manager (GCCM)
Design Complete: March 25, 2019
Groundbreaking: March 27, 2019
Construction Period: April 1, 2019 – August 2020
Dedication: TBD
School Opens | Students Move In: September 2020
Sq Ft (Increase): 97,000 (8,707)
Student capacity (Increase): 600 (120)
Total Completion Cost: $29.5 million estimated construction from 2018 construction bond and state construction match
Key Features: Complete remodel and expansion including: new entryway, safety/security upgrades, direct day light/windows in every standard classroom, new classroom furniture, updated shop area, and improved parking and on-site traffic flow.